House Extension Development Permit
Scope:
JC Engineers was approached to address a refusal notice from Ku-ring-gai Council (NSW) for a proposed house extension. Council refused the application due to the following reasons:
-
Exceed Building Height Restrictions
-
Inadequate Stormwater Planning
-
Lack of Erosion and Sediment control
-
Privacy Concerns
-
Bulk & Aesthetics Issues
-
Lack of adequate Landscaping
Solution:
Our Planning team reviewed the building plans and identified areas of non-compliance. Recommendations to achieve compliance were provided to the building designer. JCE completed all outstanding specialist documents (i.e. Stormwater Management Plan, Erosion and Sediment Control & Landscape Plans) to be included in the Development Application.
​
A Statement of Environmental Effects was prepared to justify the aspects of non compliance within the Development Control Plan.
Timeframe: Our team completed all relevant works within 3 weeks of engagement. The application was lodged with Ku-ring-gai Council, where our planners managed the application until a decision notice was issued.